OpenList

Planning application 2360313

The development of grid connection infrastructure comprising the laying of c.

In or in the vicinity of the townlands of Garrymore Upper Ballyteige Tansleyclose Knocakadosan Ballygannon Ballinderry Upper Ballinderry Lower and Copse , Co. Wicklow

Decision

CONDITIONAL

Construction status

Construction commenced

Official building-control evidence dated 14 Apr 2025.

Matched phased building-control records

Source: NBCO/BCMS open data

Application details

Planning reference
2360313
Council
Wicklow County Council
Proposal description
The development of grid connection infrastructure comprising the laying of c. 4.43 kilometres (4,430 metres) of 38kV underground electricity cables in ducts and associated infrastructure substantially under public roads to connect the solar photovoltaic (“PV”) energy development on lands at Garrymore Upper, Rathdrum Co. Wicklow approved under Register Reference 16/1099: PL 27.247942 to a new electricity substation adjacent to the ESB Rathdrum 38kV Substation to the south of Zoetis Belgium SA, The Copse, Rathdrum, Co. Wicklow (part of site that is subject to an Industrial Emissions Licence)
Location / address
In or in the vicinity of the townlands of Garrymore Upper Ballyteige Tansleyclose Knocakadosan Ballygannon Ballinderry Upper Ballinderry Lower and Copse , Co. Wicklow
Application type
PERMISSION
Received / registered
27 Sept 2023
Council decision
CONDITIONAL
Council decision date
21 Nov 2023
Final grant date
3 Jan 2024

Planning and construction timeline

Key dated milestones from planning, appeal and official building-control records.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

  4. Works commenced

    Official NBCO/BCMS data
  5. Completion certificate validated (1 unit)

    Official NBCO/BCMS data

Location context

Nearby sold prices

Recent Property Price Register sales in Ballinderry. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices