OpenList

Planning application 17601

Solar farm within a site area of approximately 27 hectares consisting of solar photovoltaic panels covering an area up…

Milltown North & Cronroe, Rathnew, Co. Wicklow

Decision

CONDITIONAL

Construction status

Construction commenced

Latest milestone

Completion certificate validated (1 unit)

25 Apr 2022

Application timeline

Key milestones

Planning, appeal and official building-control milestones.

  1. Application received

  2. Decision: CONDITIONAL

  3. Appeal lodged

  4. Appeal decided

  5. Works commenced

    Official NBCO/BCMS data
  6. Completion certificate validated (1 unit)

    Official NBCO/BCMS data

Application details

Planning reference
17601
Council
Wicklow County Council
Proposal description
Solar farm within a site area of approximately 27 hectares consisting of solar photovoltaic panels covering an area up to 182,120 sqm on ground mounted steel frames, 1 no on site substation, 6 no inverter / transformer stations, underground cables and ducts, boundary security fence, new internal tracks, CCTV cameras and all associated site services and works. The permission is sought for a period of 10 years
Location / address
Milltown North & Cronroe, Rathnew, Co. Wicklow
Application type
PERMISSION
Received / registered
25 May 2017
Council decision
CONDITIONAL
Council decision date
18 Jul 2017
Appeal lodged
9 Aug 2017
Appeal decision date
9 Feb 2018

Location context

Nearby sold prices

Recent Property Price Register sales in Rathnew. Distances are not shown because the sale records do not contain reliable coordinates.