Planning application 2660445

Development which will consist of refurbishment works to 24.2 kilometres (km) of OHL; comprising provision of fibre wrap…

Located along the Blundelstown – Mullingar 110 kilovolt (kV) overhead line (OHL) , commencing within Blundelstown in the townland of Harlockstown Co. Meath , and extending to the existing Mullingar 110kV substation in the townland of Irishtown Cou

Current status

Pre-validation

Decision due

Council record currently gives this as the decision due date.

Application details

Planning reference
2660445
Council
Westmeath County Council
Proposal description
Development which will consist of refurbishment works to 24.2 kilometres (km) of OHL; comprising provision of fibre wrap; replacement of 7 no. steel towers; replacement of 73 no. pole-sets/poles; replacement of 9 no. pole-set cross arms only; refurbishment work to 19 no. wooden pole-sets; and the treatment and painting of 2 no. steel towers. These structures (No’s. 182-299) and the associated OHL lie between where the OHL crosses the border into County Westmeath in the townland of Grange More, to where the OHL ties-in to the existing Mullingar 110kV substation in the townland of Irishtown, crossing the County Westmeath townlands of Grange More, Craddanstown, Joristown Lower, Priesttown, Clonreagh, Corbetstown, Higginstown, Hodgestown, Millerstown, Corbally, Edmondstown, Clonlost, Clonickilvant, Ballycor, Aghadaugh, Killynan (Cooke), Mountrobert, Macetown, Rathconnell, Clonsheever, Culleen Beg, Robinstown (Levinge), Ballyglass and Irishtown. The Proposed Development also includes 1 no. temporary Construction Compound in the townland of Aghadaugh. The refurbishment works in County Westmeath will consist of: the replacement (‘restringing’) of the existing OHL circuit conductor wires; the installation of fibre wrap; replacement of 7 no. steel towers and 73 no. wooden pole-sets/poles with similar dimensions and heights as the existing (replacement towers will be no more than 0.5m taller than existing and replacement pole-sets/poles will be no more than 3m taller than existing); installation of replacement parts on towers and pole-sets; foundation refurbishment / strengthening and recapping / clearing of shear blocks; treatment and painting of towers to be retained; all associated site development works, including temporary works areas; clearance of shear block bases; vegetation maintenance works; ancillary site preparation works, site clearance and levelling at the 1 no. temporary construction compound; temporary works to existing tracks and new temporary access routes to each structure, one of which is within the curtilage of Millerstown House (protected structure RPS No. 020-050), in the townland of Millerstown; and all associated works required to facilitate the Proposed Development A Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application.
Location / address
Located along the Blundelstown – Mullingar 110 kilovolt (kV) overhead line (OHL) , commencing within Blundelstown in the townland of Harlockstown Co. Meath , and extending to the existing Mullingar 110kV substation in the townland of Irishtown Cou
Application type
PERMISSION
Received / registered
24 Aug 2026

Planning timeline

Key dated milestones from the planning record.

  1. Application received

  2. Decision due

    Target date

    Current decision target recorded by the council.

Location context

Nearby sold prices

Recent Property Price Register sales in Mullingar. Distances are not shown because the sale records do not contain reliable coordinates.