Planning application 19183
For a solar farm of up to 30 megawatt (mw) located at two sites in Curraghduff townland (northern parcel)…
Mothel & Curraghduff townlands, Co. Waterford.
Application timeline
Key milestones
Key dated milestones from the planning record.
Application received
Decision: CONDITIONAL
Appeal lodged
Appeal decided
Application details
- Planning reference
- 19183
- Council
- Waterford City and County Council
- Proposal description
- For a solar farm of up to 30 megawatt (mw) located at two sites in Curraghduff townland (northern parcel) and in Mothel townland (southern parcel) comprising of: photovoltaic panels on ground mounted steel frames on an area of approximately 145,000 square meters, up to 24 no. battery storage containers, up to 4 no. inverter / transformer stations, one storage container, new site access, temporary construction compound / material storage area in northern parcel; photovoltaic panels on ground mounted steel frames on an area of approximately 50,000 square meters, up to 2 no. inverter / transformer stations, one storage container, new site access and temporary construction compound / material storage area in southern parcel; and underground cables and ducts, perimeter fencing and access gates, CCTV and all ancillary development services and work. Permission sought for a period of ten years and 30 year operational life from the date of commissioning of the solar farm. A Natura Impact Statement (NIS) is submitted with the planning application
- Location / address
- Mothel & Curraghduff townlands, Co. Waterford.
- Application type
- PERMISSION
- Received / registered
- 21 Mar 2019
- Council decision
- CONDITIONAL
- Council decision date
- 14 May 2019
- Appeal lodged
- 10 Jun 2019
- Appeal decision date
- 27 Sept 2019
Location context
Nearby sold prices