OpenList

Planning application 2560940

A Battery Energy Storage System (BESS) development to consist of a new site entrance and access track…

Ballygammane and adjacent to the existing Thurles 110kV substation, Thurles, Co. Tipperary

Decision

CONDITIONAL

Latest milestone

Final grant

16 Aug 2026

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Further information requested

  3. Further information received

  4. Decision: CONDITIONAL

  5. Final grant

Application details

Planning reference
2560940
Council
Tipperary County Council
Proposal description
A Battery Energy Storage System (BESS) development to consist of a new site entrance and access track, site security fencing including a noise acoustic barrier, access gates, BESS enclosures, a BESS intake substation, MV skid, a back-up generator, a monitoring house, an auxiliary transformer, spares containers, CCTV, an onsite toilet, carparking, a temporary construction stage compound area, landscaping and all associated ancillary development services and works, all to be provided within a total overall application boundary of 2.69 ha. Permission is sought for the proposed BESS development for a period of 10 years with an operational period of 40 years. An Appropriate Assessment Screening Report (AASR) and Natura Impact Statement (NIS) has been prepared for this development and submitted with this planning application. A separate application will be submitted to An Coimisiún Pleanála to obtain permission for a 110kV substation on site
Location / address
Ballygammane and adjacent to the existing Thurles 110kV substation, Thurles, Co. Tipperary
Application type
PERMISSION
Received / registered
22 Sept 2025
Council decision
CONDITIONAL
Council decision date
13 Jul 2026
Final grant date
16 Aug 2026

Location context

Nearby sold prices

Recent Property Price Register sales in Thurles. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices