OpenList

Planning application 2260420

A solar PV development on a 92 ha site consisting of: - The erection of solar panels on ground-mounted galvanised steel…

Barnanalleen, Moanmore and, Seskin

Decision

Granted with conditions

Latest milestone

Final grant

8 Nov 2022

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Application details

Planning reference
2260420
Council
Tipperary County Council
Proposal description
A solar PV development on a 92 ha site consisting of: - The erection of solar panels on ground-mounted galvanised steel frames, 198 no. string inverters attached to selected ground-mounted galvanised steel frames, 8 no. transformer units, underground cabling, security fencing, CCTV system with pole mounted cameras and landscaping; - 3 no. site entrances with access gates utilizing existing farm field entrances which will be upgraded and internal accesses; - 1 no. on-site IPP switching substation and associated works abutting the existing Cauteen 110kv substation; - a temporary construction compound; and - all associated ancillary development works; at Barnanalleen, Moanmore and Seskin, County Tipperary. The development can operate as an independent solar PV development and in conjunction with the solar PV developments permitted under planning permission references 17/600456 and 21/1109. The operational lifespan of the solar PV development will be 35 years. A Natura Impact Statement will accompany the planning application.
Location / address
Barnanalleen, Moanmore and, Seskin
Application type
PERMISSION
Received / registered
16 Aug 2022
Council decision
CONDITIONAL
Council decision date
5 Oct 2022
Final grant date
8 Nov 2022

Location context

Nearby sold prices

Recent Property Price Register sales in Moanmore. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices