OpenList

Planning application 211819

Alterations to the previously granted solar farm (Tipperary County Council Reg Ref 17600928) Permission was originally…

Deerpark, Carrick-on-Suir, Co. Tipperary

Decision

Granted with conditions

Latest milestone

Final grant

22 Mar 2022

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Application details

Planning reference
211819
Council
Tipperary County Council
Proposal description
Alterations to the previously granted solar farm (Tipperary County Council Reg Ref 17600928) Permission was originally granted for a solar photovoltaic installation comprising arrays of approximately 13,770 solar PV panels on ground mounted frames no taller than 2.8m; 2 no. inverter/transformer container units; a battery storage container unit; a 20kV on-site substation; landscaping, fencing and CCTV cameeras around the solar PV arrays and connecting to the off-site Deerpark ESB substation; provision of a temporary construction compound; widening of the existing farm entrance and internal tracks; and all ancillary works on a site of 9.12 ha. Permission is now sought for the following: optimised solar pv panel configuration to comprise up to 23,581 m" of solar panels on ground mounted frames; increase in height to the permitted solar panels from 2.72m to 2.82m and; Permission for an operational period of the solar farm from 35 years. Planning Permission is sought for a period of 10 years
Location / address
Deerpark, Carrick-on-Suir, Co. Tipperary
Application type
PERMISSION
Received / registered
15 Dec 2021
Council decision
CONDITIONAL
Council decision date
16 Feb 2022
Final grant date
22 Mar 2022