Planning application SD22A/0312

Construction of a single storey Discount Foodstore Supermarket with ancillary off-licence use (with mono­pitch roof…

Main Street Upper, Newcastle, Co Dublin

Decision

Grant Permission

Construction status

Construction commenced

Official building-control evidence dated 2 Jan 2024.

Matched phased building-control records

Source: NBCO/BCMS open data

Application details

Planning reference
SD22A/0312
Council
South Dublin County Council
Proposal description
Construction of a single storey Discount Foodstore Supermarket with ancillary off-licence use (with mono­pitch roof and overall building height of c. 6.74 metres) measuring c. 2,207sq.m gross floor space with a net retail sales area of c. 1,410sq.m; Construction of a vehicular access point to Main Street Upper and associated works to carriageway and including partial removal of boundary wall / facade, modification of existing footpaths / public realm and associated and ancillary works including proposed entrance plaza area; Demolition of part of an existing rear / southern single storey residential extension (and related alterations to remaining structure) of Kelly Estates building; The original Kelly Estates building (a protected structure - Eircode: D22 Y9H7) will not be modified; Demolition of detached single storey accommodation/ residential structure and ancillary wall/ fence demolitions to rear of existing Kelly Estates building; Demolition of existing single storey (stable) building along Main Street and construction of single storey retail /cafe unit on an extended footprint measuring c. 118sq.m and associated alterations to existing Main Street boundary facade; Renovation and change of use of existing (vacant) two storey vernacular townhouse structure to Main Street, and single storey extension to rear, for retail/ commercial use (single level throughout) totalling c. 61sq.m; Repair and renewal of existing Western and Eastern burgage plot tree and hedgerow site boundaries; Provision of associated car parking, cycle parking (and staff cycle parking shelter), pedestrian access routes and (ramp and stair) structures (to / through the southern and western site boundaries to facilitate connections to potential future development), free standing and building mounted signage, free standing trolley bay cover /enclosure, refrigeration and air conditioning plant and equipment, roof mounted solar panels, public lighting, hard and soft landscaping, boundary treatments and divisions, retaining wall structures, drainage infrastructure and connections to services/ utilities, electricity Substation and all other associated and ancillary development and works above and below ground level including within the curtilage of a protected structure.
Location / address
Main Street Upper, Newcastle, Co Dublin
Application type
Permission
Received / registered
9 Mar 2023
Council decision
Grant Permission
Council decision date
5 Apr 2023
Final grant date
15 May 2023

Planning and construction timeline

Key dated milestones from planning, appeal and official building-control records.

  1. Application received

  2. Decision: Grant Permission

  3. Final grant

  4. Works commenced

    Official NBCO/BCMS data
  5. Works commenced

    Official NBCO/BCMS data
  6. Completion certificate validated (1 unit)

    Official NBCO/BCMS data
  7. Completion certificate validated (1 unit)

    Official NBCO/BCMS data

Location context

Nearby sold prices

Recent Property Price Register sales in Main Street. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices