Planning application 2360214
A 10 year planning permission for the construction of a: 1.
Townland of Ballysumaghan Fannybrook, Quarry Lane Co. Sligo, Ireland
Application timeline
Key milestones
Key dated milestones from the planning record.
Application received
Decision: CONDITIONAL
Final grant
Application details
- Planning reference
- 2360214
- Council
- Sligo County Council
- Proposal description
- A 10 year planning permission for the construction of a: 1. enclosed battery energy storage system compound on a total of up to c. 5.05 hectare site, to include: • 150 battery units set inside storage blocks on concrete support structures containing Heating, ventilation and air conditioning unit (HVAC units); • Transformer and inverter units on concrete support structures; • 1 no. two storey customer 220kV Gas Insulated Substation (GIS) (See Drawing 23553-201 and 23552-202); • 1No. Customer Control Building and 220kV Transformer with associated Switchgear; • 3No. Containing Back-up Generators, Auxiliary Transformers, Switchgear containers, LV and Control Containers; • 1No. Lightning Pole; • 2No. Firewater reservoir ponds with Pumping station and 1No. detention basin with associated drainage systems (as per Drawing 23553-102); • Security gates, 2.6m palisade perimeter security fencing, CCTV and lighting system, landscaping works and all associated ancillary infrastructure; • 4.5m wide Access tracks and site entrance along with upgrade works on the public site access road (c.950m), • Associated electrical cabling and ducting and all other ancillary and miscellaneous site works including site clearance; site access, internal roads and development of areas of hard standing including a maintenance lay-down area. • c.100m of underground cabling ducts and cable to the neighbouring ESB substation. A Natura Impact Statement has been prepared for this proposed development to assess and mitigate any potential ecological impacts. the development will be located at a site in the townland of Ballysumaghan, Fannybrook, Quarry Lane Co. Sligo. The proposed development will have a projected life span of 35 years.
- Location / address
- Townland of Ballysumaghan Fannybrook, Quarry Lane Co. Sligo, Ireland
- Application type
- PERMISSION
- Received / registered
- 17 Aug 2023
- Council decision
- CONDITIONAL
- Council decision date
- 10 Oct 2023
- Final grant date
- 14 Nov 2023
Location context
Nearby sold prices
OpenList shows sold-price context only where a reliable proximity, Eircode or locality relationship can be established.
No reliable nearby sold-price match is available for this record. OpenList does not infer an exact property match from an address alone.