Planning application 2360288

Planning permission for a renewable wind energy development of a one (1) turbine wind farm.

Riverstown , Gorteen , Co. Sligo

Appeal decision

Grant permission with revised conditions

Council status: APPLICATION FINALISED

Application details

Planning reference
2360288
Council
Sligo County Council
Proposal description
Planning permission for a renewable wind energy development of a one (1) turbine wind farm. The proposed development will be located in the townland of Riverstown, approximately 2.2km north of Gorteen, Co. Sligo. The development will comprise of one (1) electricity generating wind turbine, which will have an overall maximum tip height of 180 meters, comprising a tower of nominally 112 meters high, and rotor diameter of up to 136 meters. The development will consist of permanent access tracks, hardstandings, an electrical substation building, an underground cable trench and ancillary site works. The maximum output capacity of the wind farm will be c.3.5mw.
Location / address
Riverstown , Gorteen , Co. Sligo
Application type
PERMISSION
Received / registered
24 Oct 2023
Council status
APPLICATION FINALISED
Council decision
CONDITIONAL
Council decision date
4 Jul 2024
Appeal lodged
29 Jul 2024
Appeal decision
Grant permission with revised conditions
Appeal decision date
2 Dec 2025

Planning timeline

Key dated milestones from the council planning record and An Coimisiún Pleanála appeal records.

  1. Application received

  2. Decision: CONDITIONAL

  3. Appeal lodged with An Coimisiún Pleanála

    Official An Coimisiún Pleanála dataView appeal case
  4. Appeal decision: Grant permission with revised conditions

    Official An Coimisiún Pleanála dataView appeal case

Location context

Nearby sold prices

Recent Property Price Register sales in Riverstown. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices