Planning application 2660230
Ballyboughlin Solar Park 38kV Grid Connection
Townlands of Lehinch Kilcoursey Kilbride Aghamore Raheen and Clara, near Clara, Co. Offaly
Current status
Further information received
Council status: NEW APPLICATION
Next key date
Decision due
10 December 2026
Application timeline
Key milestones
Key dated milestones from the planning record.
Application received
Further information requested
Further information received
Decision due
Target dateCurrent decision target recorded by the council.
OpenList context
Why this application matters
Grid connection
A hybrid 38kV connection is proposed between the permitted Ballyboughlin Solar Park and the existing Clara 38kV Substation.
Route and infrastructure
The route comprises about 4.5km of underground cable along public roads and about 898m of overhead line, with five joint bays, ducting and associated works.
Linked solar project
The connection serves the permitted Ballyboughlin Solar Park, a roughly 14MW solar PV farm off Curragh Road (L20171) in the Clara townland.
Environmental assessment
A Natura Impact Statement assesses construction and operation of the grid connection alongside the wider solar park infrastructure.
OpenList context is an AI-assisted interpretation of public planning records. Application status and formal decisions are shown separately from this editorial context.
Application details
- Planning reference
- 2660230
- Council
- Offaly County Council
- Proposal description
- (RED 111) a 38kV hybrid grid connection cable and is intended to connect the permitted Ballyboughlin Solar Park (Pl. Ref. 24/60338) to the existing Clara 38kV Substation. The proposed development will consist of: The laying of a 38kV underground electrical grid connection cable (c.4.5km in length), utilising public roads, and the construction of an overhead electrical grid connection cable (c. 0.898km in length), from the existing Clara 38kV substation to the permitted Ballyboughlin Solar Park (Pl. ref. 24/60338). The proposed development includes all associated site development and site enabling works and ancillary infrastructure, including 5 no. joint bays and 38kV underground ducting and cabling. A Natura Impact Statement (NIS) accompanies this Planning Application. The NIS assesses both the construction and operation of the Proposed Development, as well as integral elements of the wider project infrastructure, comprising the permitted Ballyboughlin Solar Park (Pl. Ref. 24/60338) which consists of the construction and operation of c. 14MW solar photovoltaic (PV) farm located off Curragh Road (L20171) in the townland of Clara, near Clara, Co. Offaly and all associated works. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply
- Location / address
- Townlands of Lehinch Kilcoursey Kilbride Aghamore Raheen and Clara, near Clara, Co. Offaly
- Application type
- PERMISSION
- Received / registered
- 29 Apr 2026
- Valid date
- 29 Apr 2026
- Council status
- NEW APPLICATION
Location context
Nearby sold prices
Recent Property Price Register sales in Kilcoursey. Distances are not shown because the sale records do not contain reliable coordinates.
€380,000
1 HEATHER GROVE, KILCOURSEY, CLARA
Sold 3 Jul 2026
Locality match
€418,000
IVY LODGE, KILCOURSEY, CLARA
Sold 12 Dec 2025
Locality match
€145,000
50 BEECHMOUNT AVE, KILCOURSEY, CLARA
Sold 12 Aug 2025
Locality match
€266,000
52 HEATHER GROVE, KILCOURSEY, CLARA
Sold 7 Jun 2024
Locality match
€236,000
17 ABBEYCOURT, KILCOURSEY, CLARA
Sold 26 Feb 2024
Locality match
€185,000
33 SILVERDALE EST, KILCOURSEY, CLARA
Sold 25 Oct 2023
Locality match