Planning application 2460485
The proposed development includes the construction of the following…
Lumcloon , Cloghan , County Offaly
Appeal decision
Grant permission with revised conditions
Council status: APPLICATION FINALISED
Application details
- Planning reference
- 2460485
- Council
- Offaly County Council
- Proposal description
- The proposed development includes the construction of the following: (i) two new independent power provider (IPP) buildings, (ii) two new electrical transformers, (iii) additional air insulated switchgear (AIS) including four new 110kV bays, (v) connection to the grid via the existing 110kV Derrycarney substation, (vi) access to the site is proposed through an upgraded existing entrance onto the R357 regional road consented under planning reference 23/60111 and through the existing Derrycarney 110kV Substation entrance, (vii) all civil engineering works, drainage, internal roads, landscaping, lighting, temporary construction compound and security fencing.
- Location / address
- Lumcloon , Cloghan , County Offaly
- Application type
- PERMISSION
- Received / registered
- 5 Dec 2024
- Council status
- APPLICATION FINALISED
- Council decision
- CONDITIONAL
- Council decision date
- 6 Feb 2025
- Appeal lodged
- 5 Mar 2025
- Appeal decision
- Grant permission with revised conditions
- Appeal decision date
- 7 Jul 2025
Planning timeline
Key dated milestones from the council planning record and An Coimisiún Pleanála appeal records.
Application received
Decision: CONDITIONAL
Appeal lodged with An Coimisiún Pleanála
Official An Coimisiún Pleanála dataView appeal caseAppeal decision: Grant permission with revised conditions
Official An Coimisiún Pleanála dataView appeal case
Location context
Nearby sold prices
Recent Property Price Register sales in Lumcloon. Distances are not shown because the sale records do not contain reliable coordinates.