Planning application 22664
EIRGRID PLC (WITH THE CONSENT AND APPROVAL OF THE ELECTRICITY SUPPLY BOARD (ESB))…
DERRYIRON 110KV SUBSTATION, CLONIN RHODE, CO. OFFALY
Decision
CONDITIONAL
Construction status
Construction commenced
Latest milestone
Works commenced
16 May 2024
Application timeline
Key milestones
Planning, appeal and official building-control milestones.
Application received
Decision: CONDITIONAL
Final grant
Works commenced
Official NBCO/BCMS data
Application details
- Planning reference
- 22664
- Council
- Offaly County Council
- Proposal description
- EIRGRID PLC (WITH THE CONSENT AND APPROVAL OF THE ELECTRICITY SUPPLY BOARD (ESB)), INTENDS TO APPLY FOR PERMISSION FOR DEVELOPMENT AT SITE OF APPROXIMATELY 1 HECTARE AT DERRYIRON 110KV SUBSTATION, CLONIN, RHODE, CO. OFFALY. DEVELOPMENT CONSISTING OF WORKS TO UPGRADE THE EXISTING SUBSTATION INCLUDING: THE INSTALLATION OF ADDITIONAL AIR INSULATED SWITCHGEAR ELECTRICAL APPARATUS (APPROXIMATELY 7M IN HEIGHT) TO FACILITATE THE PROVISION OF A 110KV BUSBAR; INSTALLATION OF 3 NO. ADDITIONAL BAYS (EACH CONSISTING OF BUSBAR DISCONNECTS, SECTIONALISERS, CIRCUIT BREAKERS, CURRENT TRANSFORMERS, VOLTAGE TRANSFORMERS, LINE TRAPS, COUPLING CAPACITORS AND OTHER ELECTRICAL APPARATUS); AN EXTENSION TO THE NORTH OF THE EXISTING CONTROL BUILDING (APPROXIMATELY 73 SQUARE METERS) TO PROVIDE ACCOMMODATION FOR CABINETS, OTHER ELECTRICAL APPARATUS AND A BATTERY ROOM; INSTALLATION OF 2 NO. CIRCUIT BYPASS ARRANGEMENTS (APPROXIMATELY 14M AND APPROXIMATELY 4M IN HEIGHT, RESPECTIVELY) TO FACILITATE NORMAL OPERATION OF THE SUBSTATION DURING CONSTRUCTION; AND AN EXTENSION TO THE HARDSTAND COMPOUND (APPROXIMATELY 0.03 HECTARES). THE DEVELOPMENT WILL ALSO CONSIST OF: ALL ANCILLARY AND ASSOCIATED ELECTRICAL WORKS TO FACILITATE THE PROPOSED DEVELOPMENT; AND ALL OTHER ASSOCIATED SITE EXCAVATION, INFRASTRUCTURAL AND SITE DEVELOPMENT WORKS ABOVE AND BELOW GROUND, INCLUDING SITE PREPARATION WORKS, SITE CLEARANCE AND LEVELLING; HARDSTANDING, INTERNAL ACCESS TRACKS AND TEMPORARY CONSTRUCTION COMPOUND; EARTHGRID, SURFACE WATER DRAINAGE NETWORK; PALISADE FENCING (APPROXIMATELY 2.7M HIGH) AND GATES; AND LANDSCAPING.
- Location / address
- DERRYIRON 110KV SUBSTATION, CLONIN RHODE, CO. OFFALY
- Application type
- PERMISSION
- Received / registered
- 21 Dec 2022
- Council decision
- CONDITIONAL
- Council decision date
- 23 Feb 2023
- Final grant date
- 30 Mar 2023
Location context
Nearby sold prices
Recent Property Price Register sales in Co Offaly. Distances are not shown because the sale records do not contain reliable coordinates.
€180,000
KILLURIN, CO. OFFALY, R35 A384
Sold 18 Jun 2026
Locality match
€206,000
48 CARRAIG EAN, CO. OFFALY, OFFALY
Sold 26 Feb 2026
Locality match
€164,000
54 CARRAIG EAN, CO. OFFALY, OFFALY
Sold 5 Jul 2023
Locality match
€20,000
54 Carraig Ean, Co. Offaly, Offaly
Sold 13 Jul 2017
Locality match
€20,000
58 Carraig Ean, Co. Offaly, Offaly
Sold 13 Jul 2017
Locality match