OpenList

Planning application 2198

A PERIOD OF 5 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 60.53 HECTARES…

BALLYTEIGE LITTLE BALLYTEIGE BIG AND COLEHILL, TULLAMORE, CO. OFFALY

Decision

CONDITIONAL

Latest milestone

Final grant

3 Mar 2022

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Application details

Planning reference
2198
Council
Offaly County Council
Proposal description
A PERIOD OF 5 YEARS TO CONSTRUCT AND COMPLETE A SOLAR PV ENERGY DEVELOPMENT WITH A TOTAL SITE AREA OF 60.53 HECTARES, TO INCLUDE A SINGLE STOREY ELECTRICAL SUBSTATION BUILDING, INVERTER SUBSTATIONS, MODULES, SOLAR PV GROUND MOUNTED ON SUPPORT STRUCTURES, A TEMPORARY CONSTRUCTION COMPOUND, INTERNAL ACCESS TRACKS, SECURITY FENCING, ELECTRICAL CABLING AND DUCTING, CCTV AND OTHER ANCILLARY INFRASTRUCTURE, DRAINAGE, ADDITIONAL LANDSCAPING AND HABITAT ENHANCEMENT AS REQUIRED AND ASSOCIATED SITE DEVELOPMENT WORKS RELATING TO THE ACCESS OF THE SITE. THE SOLAR FARM WILL BE OPERATIONAL FOR 35-YEARS
Location / address
BALLYTEIGE LITTLE BALLYTEIGE BIG AND COLEHILL, TULLAMORE, CO. OFFALY
Application type
PERMISSION
Received / registered
3 Mar 2021
Council decision
CONDITIONAL
Council decision date
25 Jan 2022
Final grant date
3 Mar 2022

Location context

Nearby sold prices

Recent Property Price Register sales in Tullamore. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices