OpenList

Planning application 20237

DEVELOPMENT OF A COMBINED HEAT AND POWER GENERATING BIOMASS GASIFICATION PLANT WITH INTEGRATED CARBON CAPTURE…

COOLCOR, RHODE, CO OFFALY

Decision

Granted with conditions

Latest milestone

Final grant

22 Jun 2021

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Application details

Planning reference
20237
Council
Offaly County Council
Proposal description
DEVELOPMENT OF A COMBINED HEAT AND POWER GENERATING BIOMASS GASIFICATION PLANT WITH INTEGRATED CARBON CAPTURE AND UTILISATION TECHNOLOGY TO PROVIDE RENWABLE ENERGY AND ELECTRICAL GRID SUPPORT SERVICES ON A 2.45-HECTARE SITE. THE DEVELOPMENT WILL COMPRISE: (I) OPEN AREA FEEDSTOCK RECEPTION BUNKERS (GROSS AREA OF 425.58SQM), WHICH WILL PROVIDE FOR THE INTAKE AND TEMPORARY STORAGE OF BIOMASS MATERIAL FOR GASIFICATION, (II) OFFICE, WELFARE AND CONTROL ROOM BUILDING (GROSS AREA OF 110.90SQM AND 5.145M), (III) GASIFICATION PLANT (GROSS AREA OF 1,178SQM AND HEIGHT OF 20.87M)) WHICH WILL CONVERT BIOMASS INTO SYNTHETIC GAS (SYNGAS), (IV) GASIFICATION CONTROL BUILDING (GROSS AREA OF 36.97SQM AND HEIGHT OF 3.05M), (V) METHANATION UNIT (GROSS AREA OF 429SQM AND HEIGHT OF 12.83M) WHICH WILL CONVERT SYNGAS INTO RENEWABLE GAS (RNG), (VI) RNG FILLING AREA (GROSS AREA OF 451.63SQM), (VII) 2NO. BUNDED THERMAL ENERGY STORAGE TANKS (GROSS AREA OF 78.12SQM AND HEIGHT OF 10M), (VIII) GAS ENGINE COMPOUND (GROSS AREA OF 246.44SQM) CONTAINING 5NO. CONTAINERISED COMBINED HEAT AND POWER (CHP) GAS ENGINES (EACH 5.55M IN HEIGHT), (IX) ELECTRICAL SUBSTATION (GROSS AREA OF 910.8SQM) CONTAINING SWITCHYARD, ESB SUBSTATION BUILDING (GROSS AREA OF 110.62SQM AND HEIGHT OF 5.96M), ANCILLARY ELECTRICAL PLANT AND BUNDED TRANSFORMER WHICH WILL ELECTRICALLY CONNECT THE DEVELOPMENT TO THE EXISTING 110KV DERRYIRON SUBSTATION LOCATED ON LANDS TO THE SOUTH OF THE DEVELOPMENT SITE, (X) AN OPEN AREA COMPOUND CONTAINING SOLID OXIDE FUEL ELECTROLYSIS CELL (SOFEC) ENCLOSURES WHICH WILL CONVERT CARBON DIOXIDE, STEAM AND METHANE INTO RENEWABLE ENERGY, (XI) 2NO. STORE CONTAINERS, CONTAINERISED STEAM ENGINE AND CONTAINERISED HEAT RECOVERY PLANT (EACH OF GROSS AREA OF 29.77M AND HEIGHT OF 2.9M), (XII) SYNGAS AND FUEL STORAGE TANKS (GROSS AREA OF 295SQM), AND (XIII) ALL ANCILLARY DEVELOPMENT, INCLUDING; PERIMETER LANDSCAPED SOIL BERMS WITH TREE SCREENING, PERIMETER FENCING WITH ACCESS GATE AT PRIMARY VEHICLE SITE ENTRANCE WHICH WILL CONNECT THE DEVELOPMENT TO THE EXISTING ROADS OF THE ADJACENT RHODE BUSINESS PARK PROVIDING ACCESS TO THE R400, CAR PARKING, LIGHTING, INTERNAL ACCESS ROADS, WEIGHBRIDGE, CARBON FILTER, PROCESS WATER AND FIREFIGHTING WATER STORAGE TANKS AND ALL CIVIL ENGINEERING WORKS FOR THE DISPOSAL OF FOUL AND SURFACE WATER. A NATURA IMPACT STATEMENT (NIS) HAS BEEN PREPARED AND ACCOMPANIES THE PLANNING APPLICATION
Location / address
COOLCOR, RHODE, CO OFFALY
Application type
PERMISSION
Received / registered
23 Jun 2020
Council decision
CONDITIONAL
Council decision date
6 May 2021
Final grant date
22 Jun 2021

Location context

Nearby sold prices

Recent Property Price Register sales in Co Offaly. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices