Planning application 2389

Permission for the continuation of permitted development on the site (under Monaghan County Council permission ref…

St. Patrick's Direct Provision Centre , Drumgoask , Monaghan

Decision

CONDITIONAL

Application details

Planning reference
2389
Council
Monaghan County Council
Proposal description
Permission for the continuation of permitted development on the site (under Monaghan County Council permission ref: 20/22 & 22/350, comprising (1) three single storey buildings, of modular / prefabricated construction, containing a total of twenty-five units which have already been authourised under ref 20/22, with all of these dwellings providing a kitchenette, shower room with toilet and an all-purpose (living & sleeping) room as well as three further detached buildings which together contain a further twenty-nine units, which have already been authourised under ref 22/350. These latter units contain two bedrooms and a kitchen / family room, as well as bathroom and hallway accommodation. All of the above dwellings are used for asylum seekers and accommodate households of generally between one and three residents each, but could extend to cater for five residents each, depending on family size. (2) groundworks for these units comprising of the laying of foundation slabs and the creation of connections to the on-site network and the sewerage pump station which serves this direct provision centre. (3) a prefabricated laundry building; (4) two retaining walls; (5) the conversion of a vacant building into seven individual cooking facilities and two storerooms; (6) the conversion of an existing building which was formerly used as a playroom into an outlet for the supply of convenience goods to residents of this centre; (7) six plant rooms which contain heat pumps for the modular blocks at item heading (1) above; (8) two playgrounds; (9) the development utilises and existing vehicular access to the site, an existing water supply and an existing Irish Water wastewater pipeline connection (which was permitted by the council under ref 20/281); (10) the removal of existing loose stones from the site, the levelling of the land, the provision of communal open spaces, as well as a separate area for recreational purposes; (11) all ancillary site works connected with the implementation of planning permissions ref 20/22 and 22/350. Significant Further Information relates to revised plans and a planning report
Location / address
St. Patrick's Direct Provision Centre , Drumgoask , Monaghan
Application type
PERMISSION
Received / registered
16 Mar 2023
Council decision
CONDITIONAL
Council decision date
13 Jul 2023
Final grant date
17 Aug 2023

Planning timeline

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Location context

Nearby sold prices

Recent Property Price Register sales in Drumgoask. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices