Planning application AA181386

A ten year planning permission for a solar farm at this site in the townland of Muckerstown, Co.

Muckerstown, Co. Meath

Decision

CONDITIONAL

Latest milestone

Final grant

6 Mar 2019

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Application details

Planning reference
AA181386
Council
Meath County Council
Proposal description
A ten year planning permission for a solar farm at this site in the townland of Muckerstown, Co. Meath. The development will consist of the construction operation and decommissioning of a photovoltaic solar farm comprising photovoltaic panels on ground mounted frames, a 38kv DNO/Customer substation, GRP cabinet, inverter stations, switchgear substations, field transformers, auxillary transformer, monitoring house communications building, single storey storage shed, Battery containers, WC, Fencing, temporary construction compound, internal access tracks, CCTV Cameras, improvements to the existing entrance, underground cabling, landscaping, and all ancillary development works.
Location / address
Muckerstown, Co. Meath
Application type
PERMISSION
Received / registered
21 Nov 2018
Council decision
CONDITIONAL
Council decision date
22 Jan 2019
Final grant date
6 Mar 2019

Location context

Nearby sold prices

OpenList shows sold-price context only where a reliable proximity, Eircode or locality relationship can be established.

Explore sold prices
No reliable nearby sold-price match is available for this record. OpenList does not infer an exact property match from an address alone.