OpenList

Planning application 2661211

Martinstown Battery Energy Storage System

Townland of Martinstown, Athboy, County Meath

Current status

Pre-validation

Next key date

Decision due

22 November 2026

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision due

    Target date

    Current decision target recorded by the council.

OpenList context

Why this application matters

Energy storage facility

A battery energy storage system of up to 20MW peak is proposed on a 1.34-hectare site in the townland of Martinstown, Athboy. The facility is designed for a 40-year operational life.

Site infrastructure

The scheme includes 24 battery units, six transformers, a control room, switchgear, storage container and two water tanks, with fencing, CCTV, lighting, access tracks and landscaping.

Grid and access connection

Underground 33kV cabling would connect the on-site switchgear to the substation serving the adjacent Martinstown Solar Farm. Access would use and upgrade an existing entrance from the L8005 north of the site.

Environmental assessment

A Natura Impact Statement accompanies the application, covering the proposed development.

OpenList context is an AI-assisted interpretation of public planning records. Application status and formal decisions are shown separately from this editorial context.

Application details

Planning reference
2661211
Council
Meath County Council
Proposal description
RED 111 - the development will consist of a 10-year permission for the construction of a Battery Energy Storage System (BESS) on a site of approximately 1.34 hectares. It will comprise 24 no. battery energy storage system units, 6 no. transformers, 1 no. control room, 1 no. switchgear, 1 no. storage container, 2 no. water tanks, underground cabling (including a 33 kV grid connection cable from the on-site switchgear to the substation serving the adjacent Martinstown Solar Farm (Planning reference: KA161319)), fencing with access gates, 3 no. closed-circuit television (CCTV) posts, 5 no. lighting posts, 1 no. temporary construction compound, new and upgraded access tracks, and associated landscaping and ancillary works. Access to the Application Site will be provided from an existing access point off the L8005, located to the north of the Application Site. The access point will be upgraded to facilitate safe entry and exit for traffic. The development will have an operational capacity of up to 20-megawatt peak and is designed to have an operational lifetime of 40 years. A Natura Impact Statement (NIS) has been prepared and accompanies the planning application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply
Location / address
Townland of Martinstown, Athboy, County Meath
Applicant
Astro Storage Ltd
Application type
PERMISSION
Received / registered
28 Sept 2026

Location context

Nearby sold prices

Recent Property Price Register sales in Athboy. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices