Planning application 20696
SHD STAGE 3 - Application lodged with An Bord Pleanála (Stage 2 Ref. 20/69) for provision of a total of 257no…
Dublin Road, Haggardstown, Dundalk Co Louth
Decision
Granted with conditions
Construction status
Construction commenced
Latest milestone · Completion certificate validated (1 unit)
14 May 2026
This application has reached a completed planning stage. New email alerts are no longer available. Existing subscribers can review their saved alerts. My alerts
Planning data and alerts may be delayed or incomplete. Verify important updates and deadlines with the council. Data limitations.
Application timeline
Planning, appeal and official building-control milestones.
Application received
Decision: CONDITIONAL
Final grant
Works commenced
Official NBCO/BCMS dataWorks commenced
Official NBCO/BCMS dataWorks commenced (phase 1 of 3)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (2 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataWorks commenced (phase 1 of 3)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataWorks commenced (phase 1 of 3)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataWorks commenced (phase 2 of 3)
Official NBCO/BCMS dataWorks commenced (phase 2 of 3)
Official NBCO/BCMS dataCompletion certificate validated (2 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataWorks commenced (phase 3 of 3)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (0 units)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS dataCompletion certificate validated (1 unit)
Official NBCO/BCMS data
Application details
- Planning reference
- 20696
- Council
- Louth County Council
- Proposal description
- SHD STAGE 3 - Application lodged with An Bord Pleanála (Stage 2 Ref. 20/69) for provision of a total of 257no. residential units along with provision of a crèche. Particulars of the development comprise as follows: (a) Site excavation works to facilitate the proposed development to include excavation and general site preparation works along with removal of existing site compound. (b) The provision of a total of 163no. residential dwellings which will consist of the following unit mix -57no. 2 bed dwellings (house types 1, 1a, 1b) -76no. 3bed semi detached dwellings (house types 2, 2a, 2b, 3, 6) -5no. 3 bed terrace dwellings (terrace block 3) -13no.4 bed semi detached dwellings (house type 6a) -12no. 4 bed detached dwellings (house types 4 & 5) (c) The provision of a total of 94no. apartments/duplex units consisting of 19no. 1 bed units, 38no. 2bed units and 37no. 3bed units; (d) Provision of a creche; (e) Provision of associated car parking at surface level via a combination of in-curtilage parking for dwellings and via on-street parking for the creche, duplexes and apartments; (f) Provision of 4no. electric vehicle charge points adjacent to the creche building with associated site infrastructure ducting to provide charge points for residents throughout the site; (g) Provision of associated bicycle storage spaces with associated enclosures both at surface level throughout the site and bicycle storage facilities within apartment blocks 1 & 2; (h) Use of existing access from Dublin Road with associated upgrade works to facilitate vehicular, pedestrian and cycle access to include provision of a right turning lane; (i) Provision of a cycle path along Dublin Road; (j) Provision of internal access roads and footpaths and associated connections to the existing Earlsfort residential estate; (k) Provision of residential communal open space areas (including formal play areas) including all hard and soft landscape works with public lighting, planting and boundary treatments to include boundary walls, railings & fencing; (l) Provision of 2no. ESB substations; (m) Internal site works and attenuation systems to include a hydrocarbon and silt interceptor on the storm network prior to discharge to the adjacent watercourse; (n) All ancillary site development/construction works to facilitate foul, water and service networks for connection to the existing foul, water, gas and ESB networks. Number of units reduced to 216 by An Bord Pleanala
- Location / address
- Dublin Road, Haggardstown, Dundalk Co Louth
- Application type
- PERMISSION
- Received / registered
- 9 Sept 2020
- Council decision
- CONDITIONAL
- Council decision date
- 22 Nov 2020
- Final grant date
- 23 Dec 2020
Location context
Nearby sold prices
Recent Property Price Register sales in Haggardstown. Distances are not shown because the sale records do not contain reliable coordinates.
€368,848
48 St. Fursey's Park, Haggardstown, Dundalk
Sold 17 Sept 2026
Locality match
€440,000
10 MARLMOUNT GARDENS, HAGGARDSTOWN, DUNDALK
Sold 11 May 2026
Locality match
€295,154
44 St Furseys Park, Haggardstown, Dundalk
Sold 3 Apr 2026
Locality match
€535,000
DUBLIN RD EAST, HAGGARDSTOWN, DUNDALK
Sold 1 Apr 2026
Locality match
€422,907
6 ST FURSEYS LANE, HAGGARDSTOWN, DUNDALK
Sold 30 Mar 2026
Locality match
€422,907
5 st. furseys lane, haggardstown, Dundalk
Sold 26 Mar 2026
Locality match