OpenList

Planning application 22275

An underground electrical cable and transformer compound which will connect permitted solar farms within the townlands…

Kilnacarrow Ballynakill Cloonkeel Derryaroge Cloonbearla Mount Davys Cloonbony Aghamore, Lanesborough, Co Longford

Decision

CONDITIONAL

Latest milestone

Final grant

19 May 2023

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

Application details

Planning reference
22275
Council
Longford County Council
Proposal description
An underground electrical cable and transformer compound which will connect permitted solar farms within the townlands of Middleton, Ballycore, Treanboy, Newtown, Ballynakill, Bunacloy to the national grid via the proposed transformer compound at Lough Ree Power Station (within the townland of Aghamore). The Development will consist of the following components 1) and 2): 1) installation of 110kV:33kV Transformer (TRAFO) Compound on private lands at Lough Ree Power Station, within the townland of Aghamore, with associated equipment including; cable sealing end (CSE) surge arrestor (SA), earth disconnect (ED) current/voltage transformer (CT/VT) house transformer (HT) circuit breaker (CB) 1 x lightening mast (LM) at approx. 8m tall, associated underground cabling connection to the existing 110kV underground cable, diesel generator, security fence, removal of portacabins, use of and realignment of the existing access road and associated works, drainage provision, temporary construction compound and also predevelopment site investigation works. 2) installation of underground 33kV medium Voltage electrical cable with associated ducting primarily on private lands within the townlands of Kilnacarrow, Ballynakill, Cloonkeel, Derryaroge, Cloonbearla, Mount Davys, Cloonbony and Aghamore. 5.77km of the route is located on private lands with0.011km to be located on the L52652 local road and L-11623 local road. The cable installation will include the installation of 7 no. joint bays with associated communication chambers, ancillary development and also pre-development site investigation works. The underground cable is intended to connect the permitted Middleton House Solar Farm (Planning ref: 18/135) and "Middleton House Solar Farm" Bunacloy extension (Planning Ref: 21/225) to the national grid via the proposed transformer compound at Lough Ree Power Station within the townland of Aghamore. Temporary construction compounds to facilitate the installation of the cable will be located along the underground grid connection route. Part of the proposed development site lies within the boundary of Lough Ree Power Station which is licenced by the Environmental Protection Agency under an Industrial Emissions (IE) Licence Ref. P0610-02). Permission is sought for a period of 10 years
Location / address
Kilnacarrow Ballynakill Cloonkeel Derryaroge Cloonbearla Mount Davys Cloonbony Aghamore, Lanesborough, Co Longford
Application type
PERMISSION
Received / registered
8 Dec 2022
Council decision
CONDITIONAL
Council decision date
17 Apr 2023
Final grant date
19 May 2023

Location context

Nearby sold prices

Recent Property Price Register sales in Lanesborough. Distances are not shown because the sale records do not contain reliable coordinates.