OpenList

Planning application 2661142

Solar Farm and Battery Storage, Lisnagry

Grange Upper & Grange Lower, Lisnagry, Co. Limerick

Current status

Application registered

Next key date

Decision due

8 January 2027

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision due

    Target date

    Current decision target recorded by the council.

OpenList context

Why this application matters

Energy development

A solar photovoltaic farm and co-located battery energy storage system is proposed across an application area of about 19.57 hectares in Grange Upper and Grange Lower, Lisnagry.

Grid connection

The scheme would connect to Ahane 110 kV substation through an underground 10.5 kV cable, including a horizontal directional drill crossing beneath the railway.

Site infrastructure

Infrastructure includes ground-mounted panels, 34 inverter units, transformer stations, four battery enclosures, a substation building, fencing, access tracks and a new entrance from the R506.

Environmental measures

The proposal includes drainage, landscaping and biodiversity measures; a Natura Impact Statement has been prepared for the development.

OpenList context is an AI-assisted interpretation of public planning records. Application status and formal decisions are shown separately from this editorial context.

Application details

Planning reference
2661142
Council
Limerick City and County Council
Proposal description
A solar photovoltaic farm and co-located Battery Energy Storage System within an application area of approximately 19.57 hectares, comprising ground-mounted solar panels; 34 no. inverter units; 2 no. containerised LV/MV transformer stations; 4 no. battery enclosures; 2 no. Power Conversion System units; a substation building and an underground 10.5 kV grid connection to Ahane 110 kV substation, including an HDD crossing beneath the railway. The development will also include underground cabling; fencing; a gated entrance from the R506; access tracks; CCTV cameras; a temporary construction compound; a public water-main connection; a sealed underground foul-water tank with no public-sewer connection; drainage; landscaping, biodiversity measures and associated works. Construction and operational access will be from the new R506 entrance. Permission is sought for 10 years, with an operational period of 40 years. A Natura impact Statement has been prepared and will be submitted with the application. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply
Location / address
Grange Upper & Grange Lower, Lisnagry, Co. Limerick
Application type
PERMISSION
Received / registered
29 Sept 2026
Valid date
29 Sept 2026

Location context

Nearby sold prices

Recent Property Price Register sales in Lisnagry. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices