Planning application 2561367

six (6) wind turbines with a tip height of 158m, a rotor diameter of 136m and all associated foundations and hardstanding areas. A 38kV on-site substation compound containing a substation building, associated electrical equipment and transformers with separate client side and ESB entrances. The building will contain a control room, switchgear room, ESB room and store room, underground electrical and communications cabling between the wind turbines and on-site substation. Grid Connection Option A: 2.54km-long 38kV underground cable connection from the on-site substation to the existing Carrons substation to the west of the site. Grid Connection Option B: Loop into the existing 38kV onsite overhead line via the proposed 38kV substation. A new temporary site entrance off the L1219 local road to the west of the permanent site entrance for the construction phase only. Upgrade of an existing farm entrance and access track off the L1219 local road in the northwest of the site to serve as a permanent site entrance for the wind farm when operational. Approximately 3.4km of new site access tracks with associated turning areas and drainage. This includes approximately 490m of temporary access tracks which will be reinstated following construction. Upgrade of approximately 470m of existing site access tracks. A 9m-long clear span bridge crossing of the Ahacronane River by an internal site access track to the northwest of turbine T1 and an associated 1.5m x 1.0m relief culvert. A permanent meteorological mast with a height of 90m, a foundation and hardstand. Two (2) material storage areas with a total capacity of approximately 39,300m3. A temporary construction compound with an area of approximately 1,375m2. All associated site development works, including drainage, diversion or undergrounding of low voltage powerlines, landscaping and revegetation. This planning application is accompanied by an Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) which have been prepared in respect of the construction, operation and decommissioning of the proposed development, and works to facilitate turbine delivery from the port of Foynes to the wind farm site entrance via L6188, N69, L1222, L1220 and L1219. The Applicant is seeking a 10-year planning permission and 35-year operational life, initiating from the date of full commissioning of the entire wind farm. This development is covered by the provisions of the Renewable Energy Directive III (Di

within the townlands of Ballynisky Graigoor Ballyegny More Kilbradran Ballysteen Dunmoylan , Carrons and Lisbane , Co. Limerick

Current status

APPEALED

View official council application

Application details

Planning reference
2561367
Council
Limerick City and County Council
Location / address
within the townlands of Ballynisky Graigoor Ballyegny More Kilbradran Ballysteen Dunmoylan , Carrons and Lisbane , Co. Limerick
Applicant
Not recorded in source
Agent
Not recorded in source
Application type
PERMISSION
Received / registered
19 Dec 2025
Valid date
Not recorded in source
Current status
APPEALED
Decision
REFUSED
Decision date
27 Mar 2026
Final grant date
Not recorded in source
Appeal lodged
22 Apr 2026
Appeal decision date
Not recorded in source
Ward / district
Not recorded in source
Grid reference
Not recorded in source