OpenList

Planning application 2560611

Develop the following within Co.

Kilmullen Ullard or Controversyland Clonanny Lea and Loughmansland Glebe, Portarlington, Co. Laois

Appeal decision

Grant permission with conditions

Council status: APPLICATION FINALISED

Latest milestone

Appeal decision: Grant permission with conditions

22 Jul 2026

Application timeline

Key milestones

Council and An Coimisiún Pleanála milestones.

  1. Application received

  2. Decision: REFUSED

  3. Appeal lodged with An Coimisiún Pleanála

    Official An Coimisiún Pleanála dataView appeal case
  4. Appeal decision: Grant permission with conditions

    Official An Coimisiún Pleanála dataView appeal case

Application details

Planning reference
2560611
Council
Laois County Council
Proposal description
Develop the following within Co. Laois: • Linear arrays of solar PV panels on ground mounted steel supported structures with associated cabling and ducting (including onsite control and switch gear room and underground cable grid connection to the Bracklone 110kV substation); • 2 no. proposed single storey inverter stations; • A co-located Battery Energy Storage System (BESS) park (including 16 no. containers with cells and 4 no. containers with PCS and inverters) with associated security fencing and gates; • Site Perimeter fencing; • 1 no. new site entrance with palisade double security gates; • 1 no. temporary construction compound/carpark/material storage area with associated temporary site offices, parking areas and security fencing; • 1 no. temporary and 1 no. permanent steel storage containers; • Site access tracks including passing and turning bays; • On-site pole mounted CCTV cameras; • 1 no. temporary construction stage Moby Dick type wheel wash systems; • 1 no. Concrete wash out locations (within temporary construction compound); and • All associated and ancillary works The proposed solar farm development spans a total site area measuring 60.36 ha, of which 37.66 ha is located in Co. Kildare and 22.7 ha is located in Co. Laois. Permission is sought for a period of 10 years with an operational period of 40 years. The total capacity of Solar PV on the site is estimated to be 32 MW. An Appropriate Assessment Screening Report (AASR) and Natura Impact Statement (NlS) has been prepared for this development and submitted with this planning application. The development is covered by the provisions of the (RED III) Renewable Energy Directive III (Directive (EU) 2023/2413 ). The planning application is subject to section 34D of the Planning and Development Act, 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply.
Location / address
Kilmullen Ullard or Controversyland Clonanny Lea and Loughmansland Glebe, Portarlington, Co. Laois
Application type
PERMISSION
Received / registered
23 Sept 2025
Council status
APPLICATION FINALISED
Council decision
REFUSED
Council decision date
30 Dec 2025
Appeal lodged
29 Jan 2026
Appeal decision
Grant permission with conditions
Appeal decision date
22 Jul 2026

Location context

Nearby sold prices

Recent Property Price Register sales in Portarlington. Distances are not shown because the sale records do not contain reliable coordinates.