Planning application 20281
Installation of approximately 4.6 kilometers ('km') of underground cables within Carlow County Council ('CCC') boundary…
Townlands of Rossmore and Clogrennan, Co. Laois.
Application timeline
Key milestones
Key dated milestones from the planning record.
Application received
Decision: CONDITIONAL
Final grant
Application details
- Planning reference
- 20281
- Council
- Laois County Council
- Proposal description
- Installation of approximately 4.6 kilometers ('km') of underground cables within Carlow County Council ('CCC') boundary and approximately 2.0km within Laois County Council ('LCC') boundary with a voltage of up to 38 kilovolts and associated works, including a new substation with LCC, for the connection of the consented Bilboa Wind Farm (Planning Register References : Carlow County Council 11/154; An Bord Pleanala PL 01.240245) to the national electricity grid; upgrading of an existing forestry track within CCC; construction of two new onsite access track within CCC; re-orientation and increasing in size of a crane hardstanding area within CCC; and road strengthening and widening along an updated turbine delivery route, within LCC, pursuant to the consented Bilboa Wind Farm (Planning Register References: Carlow County Council 11/154; An Bord Pleanala PL 01.240245). The application is accompanied by a Planning Report, Environmental Impact Assessment Report and a Natura Impact Statement
- Location / address
- Townlands of Rossmore and Clogrennan, Co. Laois.
- Application type
- PERMISSION
- Received / registered
- 11 Jun 2020
- Council decision
- CONDITIONAL
- Council decision date
- 12 Jul 2021
- Final grant date
- 19 Aug 2021