Planning application 2560875

REDIII: The development will consist of: a 10-year permission for the development of a solar farm on an overall site of…

Site in the Townlands of Lacka More Parkmore Lissireen Tullacrimeen Aulaneduff Ballyconnell, Fahavane Knockbrack West Knocknacaska and Knocknagun, County Kerry

Current status

Application registered

Next key date

Decision due

17 October 2026

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Further information requested

  3. Further information received

  4. Decision due

    Target date

    Current decision target recorded by the council.

OpenList context

Why this application matters

Solar farm scale

The proposal covers an overall site of approximately 152.6 hectares across multiple townlands in County Kerry, with approximately 449,366 sq m of ground-mounted solar photovoltaic panels.

Energy storage and grid route

The development includes 28 battery energy storage containers, seven associated medium-voltage stations, electrical skids and underground power and communications infrastructure, including cable works along the L-6507, R557 and L-2034 roads and three horizontal directional drilling locations.

Operational infrastructure

Five solar-farm entrances, internal access tracks with passing bays, drainage, fencing, gates, CCTV and five temporary construction compounds are proposed. The solar farm is intended to operate for 40 years.

Environmental assessment

A Natura Impact Statement has been prepared for the proposed development.

OpenList context is an AI-assisted interpretation of public planning records. Application status and formal decisions are shown separately from this editorial context.

Application details

Planning reference
2560875
Council
Kerry County Council
Proposal description
REDIII: The development will consist of: a 10-year permission for the development of a solar farm on an overall site of c. 152.6 hectares consisting of the following: c. 449,366 sq m of solar photovoltaic panels on ground mounted steel frames; 19 no. hardstanding locations for electrical skids; new internal access tracks with passing bays; underground power and communications cables and ducts, including along the L-6507, R557, and L-2034 public roads, 3no. Horizontal Directional Drilling (HDD) locations associated with the underground cable route; a total of 5 no. solar farm site entrances (1no. from the R557 public road, 3no. from the L-6507 public road and 1no. from the L-10562 public road); access gates; 5no. temporary site compounds of c. 4,050 sq m each to be used for storage during construction activity; 28no. Battery Energy Storage System (BESS) Containers and 7no. associated MV Stations as well as associated CCTV, BESS compound fencing, gate, boundary fencing and all associated ancillary drainage development, site works and services. The solar farm will be operational for 40 years. A Natura Impact Statement (NIS) has been prepared in respect of the proposed development and will be submitted to the planning authority with the application.
Location / address
Site in the Townlands of Lacka More Parkmore Lissireen Tullacrimeen Aulaneduff Ballyconnell, Fahavane Knockbrack West Knocknacaska and Knocknagun, County Kerry
Application type
PERMISSION
Received / registered
26 Sept 2025

Location context

Nearby sold prices