OpenList

Planning application 221340

MODIFY THE APPROVED GRID CONNECTION FOR THE BALLYDONOHOE SOLAR FARM AS PERMITTED UNDER KERRY COUNTY COUNCIL REFERENCE…

COOLARD COOLKERAGH AND GLOURIA, LISTOWEL, CO KERRY

Decision

CONDITIONAL

Construction status

Construction commenced

Latest milestone

Construction commenced

31 Oct 2025

Application timeline

Key milestones

Planning, appeal and official building-control milestones.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

  4. Construction commenced

    Official NBCO/BCMS data

Application details

Planning reference
221340
Council
Kerry County Council
Proposal description
MODIFY THE APPROVED GRID CONNECTION FOR THE BALLYDONOHOE SOLAR FARM AS PERMITTED UNDER KERRY COUNTY COUNCIL REFERENCE 21457/AN BORD PLEANÁLA REFERENCE 312288. THE MODIFCATIONS COMPRISE OF (1) THE PROVISION OF A MV CONTROL BUILDING WITHIN THE SOLAR FARM, (2) THE LAYING OF C. 1,747 METRES OF 33KV UNDERGROUND CABLING WITH THE SOLAR FARM SITE, L-1008 AND ADJACENT PUBLIC ROAD TO BE INSTALLED IN AN EXCAVATED TRENCH INCLUDING UNDERGROUND DUCTING, JOINT BAYS, COMMUNICATION CHAMBERS AND ALL ASSOCIATED SITE DEVELOPMENT AND REINSTATEMENT WORKS, AND (3) MINOR RELOCATION OF POLE SETS AND ASSOCIATED 33KV OVER-HEAD WIRES WITHIN A C. 216 METRES SECTION OF OVERHEAD LINES ON PRIVATE LANDS
Location / address
COOLARD COOLKERAGH AND GLOURIA, LISTOWEL, CO KERRY
Application type
PERMISSION
Received / registered
21 Dec 2022
Council decision
CONDITIONAL
Council decision date
23 Feb 2023
Final grant date
29 Mar 2023

Location context

Nearby sold prices

Recent Property Price Register sales in Listowel. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices