Planning application 2461773

For: construction of 62 no. residential units comprising of: 25 no. 3 bedroom 2 storey terraced houses (Type A & Type D…

Droim Na Gaoithe & An Chreig Bhuí , Baile Chláir , Co. na Gaillimhe

Decision

CONDITIONAL

Construction status

Construction commenced

Official building-control evidence dated 6 Apr 2026.

Matched phased building-control records

Source: NBCO/BCMS open data

Application details

Planning reference
2461773
Council
Galway County Council
Proposal description
For: construction of 62 no. residential units comprising of: 25 no. 3 bedroom 2 storey terraced houses (Type A & Type D blocks), 6 no. 3 bedroom 2 storey semi-detached houses (Type C blocks), 3 no. 2 bedroom 2 storey terraced houses (Type B Block), 3 no. 2 bedroom two storey terraced houses and 1 no. 3 bedroom end of terrace house (Type H Block), 10 no. 1 bedroom ground floor apartment units and 10 no. 2 bedroom upper floor apartments units, within 2 no. two and a half storey duplex buildings (Type E & E1 Blocks), together with communal Bin Storage. 2 no. 1 bedroom ground floor apartment units and 2 no. upper floor 2 bedroom apartments units, within a two and a half storey duplex building (Type F Block), together with communal Bin Storage. Proposed new road works along R381 (Oranmore road) to include new entrance and associated right hand turning lane, revised road markings and relocation of existing kerbed road island. Demolition of single storey dwellinghouse (Eircode H91HH2H) and domestic garage/shed, together with decommissioning/removal of existing septic tank system, and closure of vehicular entrance onto L-7110 (Lakeview Road). Demolition of 5 no. single storey agricultural sheds with farmyard and closure of 2 no. agricultural entrances onto L-7110 (Lakeview Road). Provision of public and private open spaces, play and seating areas, bicycle parking, site landscaping, revised boundary treatments, and public lighting. Provision of residential carparking including a proportion of electric charging spaces and ducting to all spaces for future electric charging points. Connection to public water main along the R381 (Oranmore Road), connection and extension to the public sewer along the R381 (Oranmore Road), provision of on- site pumping station, together with on-site surface water drainage works. Footpath connections (including proposed footpath extension along L-7110 Lakeview Road), signage locations, ESB substation and all associated site development works and services. A Natura Impact Statement will be submitted to the planning authority with this application
Location / address
Droim Na Gaoithe & An Chreig Bhuí , Baile Chláir , Co. na Gaillimhe
Application type
PERMISSION
Received / registered
19 Dec 2024
Council decision
CONDITIONAL
Council decision date
27 Jun 2025
Final grant date
5 Aug 2025

Planning and construction timeline

Key dated milestones from planning, appeal and official building-control records.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

  4. Construction commenced (phase record)

    Official NBCO/BCMS data

Location context

Nearby sold prices

Recent Property Price Register sales in Baile Chlair. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices