10 YEAR DURATION FOR A PROPOSED WIND ENERGY AND GRID CONNECTION PROJECT…

CARROWMORE, QUIGLEY'S POINT, INISHOWEN

Appeal decision

Grant Permissions with Conditions

Council status: APPLICATION FINALISED

Latest milestone

Appeal decision: Grant Permissions with Conditions

20 Apr 2021

Application timeline

Key milestones

Council and An Coimisiún Pleanála milestones.

  1. Application received

  2. Decision: REFUSED

  3. Appeal lodged with An Coimisiún Pleanála

    Official An Coimisiún Pleanála dataView appeal case
  4. Appeal decision: Grant Permissions with Conditions

    Official An Coimisiún Pleanála dataView appeal case

Application details

Planning reference
1851230
Council
Donegal County Council
Proposal description
10 YEAR DURATION FOR A PROPOSED WIND ENERGY AND GRID CONNECTION PROJECT WITH A 30-YEAR OPERATIONAL LIFE FROM THE DATE OF COMMISSIONING. THE PROPOSED WIND ENERGY SITE WILL BE LOCATED WITHIN THE TOWNLAND OF CARROWMORE OR GLENTOGHER, QUIGLEY'S POINT, INISHOWEN, CO DONEGAL. THE PROPOSED WIND ENERGY SITE WILL CONSIST OF 6 NO. THREE BLADED WIND TURBINES WITH A MAXIMUM BASE TO BLADE TIP HEIGHT OF UP TO 124.9 METRES AND WILL INCLUDE TURBINE TRANSFORMERS; TURBINE BASES AND FOUNDATIONS, TURBINE HARDSTANDS AND TEMPORARY SET-DOWN AREAS; 1 NO. PERMANENT LATTICE ANEMOMETER "MET" MAST OF 80 METRES HEIGHT WITH FOUNDATIONS AND HARDSTANDING AREA; WIDENING AND STRENGTHENING OF EXISTING ACCESS TRACKS AND CONSTRUCTION OF NEW FLOATED AND EXCAVATED ACCESS TRACKS, JUNCTIONS AND TURNING AREAS; 1 NO. ELECTRICAL 38KV SUBSTATION WITH CONTROL BUILDING, CAR PARKING AND COMPOUND AREA WITH RELATED COMMUNICATIONS AND ELECTRICAL EQUIPMENT/PLANT WITH UNDERGROUNDED ELECTRICAL FEEDER CABLES AND COMMUNICATIONS LINES CONNECTING WIND TURBINES TO THE SWITCH ROOM CONTROL BUILDING; 2 NO. SPOIL DEPOSITION AREAS; DEDICATED HABITATE MANAGEMENT AREA; ON-SITE DRAINAGE MANAGEMENT WORKS; UPGRADE OF 3 NO. EXISTING SITE ENTRANCES; 2 NO. TEMPORARY CONSTRUCTION COMPOUNDS; 2 NO. TEMPORARY BORROW PITS AND WITH ALL OTHER ANCILLARY AND ASSOCIATED DEVELOPMENT AND INFRASTRUCTURE INCLUDING GENERAL AND EXACAVATION WORKS. THE PROPOSED UNDERGROUNDED GRID CONNECTION ROUTE WILL FACILITATE CONNECTION TO THE NATIONAL GRID AND WILL CONSIST OF THE LAYING OF A 38KV UNDERGROUND ELECTRICAL CABLE INCLUDING ALL ASSOCIATED INFRASTRUCTURE, UP-GRADING OF EXISTING TRACKS, CONSTRUCTION OF NEW ACCESS TRACKS, DRAINAGE, EXCAVATIONS, JOINT BAYS, JUNCTION BOXES/CHAMBERS, MARKER POSTS/PLATES AND ALL RELATED ACCOMMODATION WORKS, EXTENDING CIRCA. 17,620 METRES IN LENGTH, FROM THE WIND ENERGY SITE CONTROL BUILDING/ELECTRICAL COMPOUND TO THE EXISTING ESB OWNED 110KV TRILLICK SUBSTATION, IN BALLYNAHONE TOWNLAND, BUNCRANA. THE GRID ROUTE WILL PASS ALONG EXISTING PUBLIC ROADS AND PRIVATE ACCESS TRACKS WITHIN THE TOWNLANDS OF CARROWMORE OR GLENTOGHER, ILLIES, CONNAGHKINNAGOE, BALLYNAKEELOGE, FOFFENAGH, MEENAMULLAGAN, STRANACLEA, MEENKEERAGH, SORNE, OWENAKILLEW AND BARNAHONE, TULLYDUSH UPPER, ANNASLEE AND BALLYNAHONE ALL INISHOWEN, CO. DONEGAL. THE PLANNING APPLICATION IS ACCOMPANIED BY AN ENVIRONMENTAL IMPACT ASSESSMENT REPORT (EIAR) AND BY A NATURA IMPACT STATEMENT (NIS).
Location / address
CARROWMORE, QUIGLEY'S POINT, INISHOWEN
Application type
PERMISSION
Received / registered
10 Aug 2018
Council status
APPLICATION FINALISED
Council decision
REFUSED
Council decision date
11 Oct 2019
Appeal lodged
6 Nov 2019
Appeal decision
Grant Permissions with Conditions
Appeal decision date
20 Apr 2021