Planning application 26/1755
Madigan's Solar Farm, Charleville
Castleharrison, Ardnageehy, Ballynadrideen, Charleville, Co. Cork.
Current status
Further information requested
Latest milestone
Application received
30 Jun 2026
Application timeline
Key milestones
Key dated milestones from the planning record.
Application received
OpenList context
Why this application matters
Scale and phasing
The 55.55-hectare solar farm is planned as two land parcels, with construction split into two phases. It is designed for a 40-year operating life, followed by decommissioning.
Grid connection
The parcels lie on opposite sides of the proposed M20 and would be linked by underground cabling beneath the motorway and the L5529. The western parcel would connect to the consented Ardnageehy Solar Farm, with onward connection to the consented Ballyroe 110kV Substation.
Access and landscape
Existing entrances and about 2.25km of farm tracks would be used, alongside 1.47km of new internal tracks. Landscape measures include 10m tree belts along the proposed M20, around 1.536km of new hedgerow and biodiversity works.
OpenList context is an AI-assisted interpretation of public planning records. Application status and formal decisions are shown separately from this editorial context.
Application details
- Planning reference
- 26/1755
- Council
- Cork County Council
- Proposal description
- The proposed development (to be known as Madigan's Solar Farm) within the red line boundary for which permission is sought consists of: •the construction of, 40-year operation of, and subsequent decommissioning of a 55.55-hectare (137.26 acres) solar farm centred at approximately E:553,500 and N:618,400, and comprised of two parcels of land located to the west and east of the proposed M20 Motorway respectively; •the connection of the two parcels of land by means of an underground grid connection (UGC) to be constructed underneath the proposed M20 Motorway and the existing L5529 public road; •a further UGC from the proposed western parcel of the solar farm to the previously consented Ardnageehy Solar Farm (Cork Co. Co. Pl. Ref: 236099 / ABP-320298-24); and •10m-wide tree belts along both sides of the proposed M20 Motorway. The development will then be connected to the national grid at the consented Ballyroe 110kV Substation (permitted by An Coimisuin Pleanala ref. 314431-22) by way of an underground grid connection, previously determined by An Coimisiún Pleanála to be exempted development (Cork Co. Co. Pl. Ref. D/201/25 /; ACP ref. 322653-25). The proposed development is to be built in two separate phases within the 10-year planning permission period. Phase 1 will comprise of the western land parcel and all that is proposed within it, together with the underground grid connection from it to the consented Ardnageehy Solar Farm, as well as the proposed underground grid connection, linking the eastern and western land parcels underneath the proposed M20 Motorway, and the 10m wide tree belt proposed along both sides of the proposed motorway. Phase 2 will comprise of the eastern land parcel and all that is proposed within it, apart from the tree belt within it and underground grid connection linking it to the western land parcel. The proposed development will comprise of a series of ground-mounted solar photovoltaic (PV) panels mounted on pile driven ground support pole structures. The proposed development also includes electrical inverters/transformers, underground cabling and temporary construction compounds. Access to the western and eastern land parcels will utilise existing entrances onto the public roads. The proposed solar farm includes the use of approximately 2,250m existing internal farm access tracks that are not proposed to be upgraded as well as 1,470m proposed new internal access tracks. The proposed development also includes new internal gates, CCTV poles and cameras, deer-type security/boundary fencing, landscaping and biodiversity measures which includes the removal of approximately 45m of existing hedgerow and the planting of approximately 1,536m of new hedgerow, and all ancillary development works required to generate renewable energy electricity and transmit it in the townlands of Ballynadrideen, Ardnageehy and Castleharrison, Charleville, Co. Cork. In accordance with Article 239 of the Planning and Development Regulations 2001 (as amended), notice is hereby given: a) that a Natura Impact Statement will be submitted to the planning authority with the application, and b) that the Natura Impact Statement will be available for inspection or purchase at a fee not exceeding the reasonable cost of making a copy during office hours at the office of the planning authority. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413) and it is important to note that the planning application may be subject to section 34D of the Planning and Development Act 2000, as amended. When a notice issues in accordance with section 34D(b), the provisions of article 26A of the Planning and Development Regulations 2001 to 2025 shall apply. The planning application may be inspected, or purchased at a fee not exceeding the reasonable cost of making a copy, at the offices of the Planning Authority, County Hall, Carrigrohane Road, Co. Cork, during its public opening hours, i.e. 9.00a.m. to 4.00 p.m. Monday to Friday (excluding public holidays). A submission or observation in relation to the application may be made in writing to the planning authority on payment of the prescribed fee, €20, within the period of- (a) 5 weeks, or (b) 2 weeks, in the case of a planning application for small-scale solar energy equipment development or development that is the installation of a small-scale non-ground source heat pump, beginning on the date of receipt by the authority of the application, and such submissions or observations will be considered by the planning authority in making a decision on the application. The planning authority may grant permission subject to or without conditions or may refuse to grant permission.
- Location / address
- Castleharrison, Ardnageehy, Ballynadrideen, Charleville, Co. Cork.
- Applicant
- Soleire Renewables Holdings Limited
- Agent
- Entrust Limited
- Application type
- Permission
- Received / registered
- 30 Jun 2026
- Ward / district
- Municipal Districts: Municipal District of Kanturk - Mallow
- Grid reference
- 553639, 618727
Application location
Approximate map position from available planning location data.
Location context
Nearby sold prices
Recent Property Price Register sales in Charleville. Distances are not shown because the sale records do not contain reliable coordinates.
€135,000
69 MAIN STREET, CHARLEVILLE, COUNTY CORK
Sold 22 Oct 2026
Locality match
€330,000
11 PIKE FARM, CHARLEVILLE, CORK
Sold 15 Oct 2026
Locality match
€440,000
BUTTEVANT RD, CHARLEVILLE, CORK
Sold 23 Sept 2026
Locality match
€147,500
59 HOLY CROSS PLACE, CHARLEVILLE, CO CORK
Sold 3 Sept 2026
Locality match
€211,000
15 HOLY CROSS PLACE, CHARLEVILLE, CORK
Sold 24 Aug 2026
Locality match
€367,000
RATHGOGGIN SOUTH, CHARLEVILLE, CO. CORK
Sold 11 Aug 2026
Locality match