Planning application 25/6877

Littlesilver Battery Storage Facility

Littlesilver, Bandon, Co. Cork

Current status

Further information requested

Latest milestone

Application received

19 Dec 2025

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

OpenList context

Why this application matters

Energy storage scheme

A battery energy storage facility is proposed on a c. 1.29-hectare site at Littlesilver, Bandon, with 28 rechargeable battery containers and associated medium-voltage equipment.

Grid connection

The facility would connect to the Bandon 110kV substation via an underground cable, alongside diversion of an existing overhead line on the site.

Site renewal

The proposal includes demolition and removal of a decommissioned wind turbine and associated outbuilding, replacing them with a 38kV substation building and electrical compounds.

Access and drainage

Works include upgrades to the existing entrance and access tracks, parking, security and boundary fencing, landscaping, and drainage measures including a retention basin, soakaways and rainwater harvesting.

OpenList context is an AI-assisted interpretation of public planning records. Application status and formal decisions are shown separately from this editorial context.

Application details

Planning reference
25/6877
Council
Cork County Council
Proposal description
EDF Renewables Ireland Limited intend to apply for a 10 Year Permission for development at this site of c. 1.29 ha, located on lands at Littlesilver, Bandon, Co. Cork. The proposed development consists of a battery energy storage system (BESS) facility, which will comprise of rechargeable battery units contained within 28 no. c. 25 ft containers on site; 7 no. MVs units; 1 no. auxiliary transformer; a resistor, reactor and harmonic filter unit; a low voltage (LV) building and a welfare and spares container. The proposed development also involves the diversion of the existing overhead line on site and includes an underground cable, which will connect the BESS facility to the Bandon 110kV substation. The proposed development will include for the demolition and removal of the existing decommissioned wind turbine and associated outbuilding on site. The proposed development also includes the construction of a 38kV substation building with associated compounds and car parking; stock proof fencing and gateways; landscaping; foul water holding tank; rainwater harvesting tank; stone soakaways; piped infrastructure and ducting; retention basin and stone headwall; signage; security fencing; boundary treatments; lighting; CCTV; SUDs; permeable gravel area; upgrading of the existing site entrance with partial hedgerow removal; new access track and upgrading of the existing access track; and all associated site development and excavation works above and below ground. Planning permission is sought for a period of 10 years.
Location / address
Littlesilver, Bandon, Co. Cork
Applicant
EDF Renewables Ireland Limited
Agent
ÓRla Casey (Tom Phillips + Associates)
Application type
Permission
Received / registered
19 Dec 2025
Ward / district
Municipal Districts: Municipal District of Bandon - Kinsale
Grid reference
549741, 558533

Application location

Approximate map position from available planning location data.

Location context

Nearby sold prices

Recent Property Price Register sales in Bandon. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices