Planning application 25/4312

Permission for retention of a) demolition of northern building and link building formerly used as a factory…

Templemichael Whitescross Cork

Decision

Conditional Permission

Construction status

Construction commenced

Official building-control evidence dated 1 Dec 2025.

Matched phased building-control records

Source: NBCO/BCMS open data

Application details

Planning reference
25/4312
Council
Cork County Council
Proposal description
Permission for retention of a) demolition of northern building and link building formerly used as a factory, b) infilling of decommissioned water reservoir, c) construction of northern building used for light industrial, d) construction of a concrete wall and regrading of existing internal road and also change of use from factory to light industrial and permission for demolition of existing southern building formerly a factory and construction of a new building for light industrial use, replace existing roadside post & wire boundary fence with new concrete wall, new palisade fence to ESB substation and upgrade existing vehicular entrances to the site and associated site works.
Location / address
Templemichael Whitescross Cork
Applicant
Wave Electrical Services Ltd
Agent
Archetech Ltd.
Application type
Permission for Retention
Received / registered
28 Feb 2025
Valid date
13 Mar 2025
Council decision
Conditional Permission
Council decision date
26 Aug 2025
Final grant date
3 Oct 2025
Grid reference
170106.65, 79954.63

Planning and construction timeline

Key dated milestones from planning, appeal and official building-control records.

  1. Application received

  2. Decision: Conditional Permission

  3. Final grant

  4. Construction commenced

    Official NBCO/BCMS data