The Applicant is seeking permission for the construction, operation…

Polnareagha, Ardskeagh, Tullacondra, Croughta Kilmaclenine, Ballyclogh, Knockaunavaddreen, Copestown, Ballybeg, Baltydaniel East Twopothouse, Caurraghakerry, Co. Cork

Appeal decision

Grant permission with revised conditions

Council status: Application Finalised

Latest milestone

Appeal decision: Grant permission with revised conditions

21 May 2026

Application timeline

Key milestones

Council and An Coimisiún Pleanála milestones.

  1. Application received

  2. Decision: Conditional Permission

  3. Appeal lodged with An Coimisiún Pleanála

    Official An Coimisiún Pleanála dataView appeal case
  4. Appeal decision: Grant permission with revised conditions

    Official An Coimisiún Pleanála dataView appeal case

Application details

Planning reference
24/5503
Council
Cork County Council
Proposal description
The Applicant is seeking permission for the construction, operation and decommissioning of a wind energy development including: • 9 wind turbines each with a blade tip height of 175 metres, rotor diameter of 150 metres, hub height of 100 metres and a rated output of 4.5 megawatts. • Turbine Foundations, crane pad hardstanding areas and associated drainage. • Upgrade of existing site tracks and construction of new site tracks and associated drainage. • Access from the local road L5302 at Crought, Ballyclogh including a new site entrance for the construction phase and upgrading of an existing entrance for the operational phase. • An on-site 38 kilovolt electrical substation to Electricity Supply Board Networks specification to include control building with electrical infrastructure, welfare facilities supplied by rainwater harvesting and storage tank, a wastewater holding tank with high level alarm, car parking, security fencing and lighting, and all associated infrastructure, services, and site works including a temporary construction compound. • All associated underground electrical and communications cabling connecting the turbines to the proposed electrical substation. • A temporary site construction compound and associated ancillary infrastructure including welfare services, office accommodation, parking, fencing, lighting etc. • Areas for temporary storage of excavated materials. • A permanent meteorological mast of 100 metres height above ground level on a concrete base. • Installation of approximately 13.5 kilometres of 38 kilovolts underground electrical cabling, mainly within the public road, between the proposed wind farm substation to the boundary of Mallow 110 kilovolt substation at Saint Joseph’s Road Mallow. • All associated site works including site clearance and ancillary development including site drainage/Sustainable Drainage System, security gates, fencing, permanent and temporary signage, and biodiversity mitigation and enhancements, including hedgerow planting. The Applicant is seeking a 10-year duration planning permission and 35-year operational period from the date of overall commissioning of the entire wind farm. The Environmental Impact Assessment Report (EIAR) and Natura Impact Statement (NIS) will be submitted to the Planning Authority with the application.The wind farm development is proposed on a site in the townlands of Polnareagha and Ardskeagh (Templemary E.D.); and Tullacondra and Croughta, (Kilmaclenine E.D.), County Cork. The proposed grid connection will be installed underground mainly within the public road from the wind farm site at Croughta, Ballyclogh to the boundary of the 110 Kilovolts substation at Saint Joseph’s Road, Mallow passing through the townlands of Kilmaclenine, Croughta, Knockaunavaddreen, Copestown, (Kilmaclenine E.D.), Ballybeg (Buttevant E.D.), Baltydaniel East, Twopothouse, and Caurraghakerry (Caherduggan E.D); and Cloghlucas North, Curraghphadeen, Ballyviniter Upper, Ballyviniter Middle, Ballyviniter Lower, Parkadallane, Carrigoon More and Carrigoon Beg Mallow Rural E.D.).
Location / address
Polnareagha, Ardskeagh, Tullacondra, Croughta Kilmaclenine, Ballyclogh, Knockaunavaddreen, Copestown, Ballybeg, Baltydaniel East Twopothouse, Caurraghakerry, Co. Cork
Applicant
Tullacondra Green Energy Limited
Agent
Alison Harvey MIPI
Application type
Permission
Received / registered
9 Aug 2024
Valid date
16 Aug 2024
Council status
Application Finalised
Council decision
Conditional Permission
Council decision date
22 May 2025
Appeal lodged
17 Jun 2025
Appeal decision
Grant permission with revised conditions
Appeal decision date
21 May 2026
Ward / district
Municipal Districts: Municipal District of Kanturk - Mallow
Grid reference
550184, 605041

Application location

Approximate map position from available planning location data.

Location context

Nearby sold prices

OpenList shows sold-price context only where a reliable proximity, Eircode or locality relationship can be established.

Explore sold prices
No reliable nearby sold-price match is available for this record. OpenList does not infer an exact property match from an address alone.