OpenList

Planning application 23/5246

10 Year permission to develop an Energy Storage System, which will connect to the adjoining ESB Midleton 110kV…

Carrigogna Midleton Co Cork

Decision

Conditional Permission

Latest milestone

Final grant

19 Oct 2023

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: Conditional Permission

  3. Final grant

Application details

Planning reference
23/5246
Council
Cork County Council
Proposal description
10 Year permission to develop an Energy Storage System, which will connect to the adjoining ESB Midleton 110kV Electricity Substation. The proposed development will have a projected life span of 30 years. The development will consist of the construction of 1) enclosed battery energy storage system within a site compound on a total of up to c.0.83 hectare site, to include: 1 no. single storey 110kV customer substation, control and switch rooms; up to 13 battery blocks on concrete support structures including heating, ventilation and air conditioning unit (HVAC units); transformer and inverter units; including access tracks and site entrance along existing roadway; associated electrical cabling and ducting; security gates, 2.6m palisade perimeter security fencing; CCTV system; landscaping works and all other associated ancillary infrastructure.
Location / address
Carrigogna Midleton Co Cork
Applicant
Grid System Services Limted
Agent
Gráinne Blount
Application type
Permission
Received / registered
19 Jun 2023
Valid date
29 Jun 2023
Council decision
Conditional Permission
Council decision date
12 Sept 2023
Final grant date
19 Oct 2023
Grid reference
187247.62, 76099.83

Application location

Approximate map position from available planning location data.

Location context

Nearby sold prices

Recent Property Price Register sales in Midleton. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices