A 5.7MW solar farm comprising approximately 21,850 photovoltaic panels on ground mounted frames within a site area of…

Crocane Wind Farm Crocane Cloyne Co. Cork

Decision

Unconditional Permission

Latest milestone

Decision: Unconditional Permission

22 Feb 2022

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: Unconditional Permission

Application details

Planning reference
21/7429
Council
Cork County Council
Proposal description
A 5.7MW solar farm comprising approximately 21,850 photovoltaic panels on ground mounted frames within a site area of 13.95ha, 3 no. transformer/inverter stations, security fencing, CCTV and all associated site development and landscaping works at the site of the existing Crocane Wind Farm. The proposed development will connect to the grid via the existing Crocane Wind Farm substation on site. The proposed development will utilise the existing access to the existing Crocane Wind Farm - Extension of Duration to Permission granted under Planning Ref. No. 16/5269
Location / address
Crocane Wind Farm Crocane Cloyne Co. Cork
Applicant
IQ Solar Limited
Agent
Aiden O'Neill
Application type
Extension of Duration
Received / registered
22 Dec 2021
Valid date
14 Jan 2022
Council decision
Unconditional Permission
Council decision date
22 Feb 2022
Grid reference
189096.53, 65566.34

Application location

Approximate map position from available planning location data.

Location context

Nearby sold prices

Recent Property Price Register sales in Cloyne. Distances are not shown because the sale records do not contain reliable coordinates.