Planning application 21/5686

A 10 year permission for a 20kV overground and underground grid connection cable of 1.26km in length (of which c.0.43 km…

Classes Ballincollig Co. Cork

Decision

Granted with conditions

Latest milestone

Final grant

25 Jan 2022

Application timeline

Key milestones

Key dated milestones from the planning record.

  1. Application received

  2. Decision: Conditional Permission

  3. Final grant

Application details

Planning reference
21/5686
Council
Cork County Council
Proposal description
A 10 year permission for a 20kV overground and underground grid connection cable of 1.26km in length (of which c.0.43 km is located in the administrative area of Cork County and 0.83 km is located in the administrative area of Cork City) to be provided on overhead poles and in excavated trenches and include associated underground ducting and all associated site development and reinstatement works. The proposed grid connection cable will connect the solar farm substation permitted under Cork County Council planning reference 18/7410 (An Bord Pleanála reference 304045-19) which is now located within the administrative area of Cork City, with the existing 110kV Coolroe substation. The works will be carried out on private lands and within the public road. A Natura Impact Statement (NIS) has been prepared and will be submitted to the Planning Authority with the application.
Location / address
Classes Ballincollig Co. Cork
Applicant
Terra Solar II Limited
Agent
Conor Frehill
Application type
Permission
Received / registered
21 Jun 2021
Valid date
1 Jul 2021
Council decision
Conditional Permission
Council decision date
14 Dec 2021
Final grant date
25 Jan 2022
Grid reference
156389.14, 70778.86

Application location

Approximate map position from available planning location data.

Location context

Nearby sold prices

Recent Property Price Register sales in Ballincollig. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices