Planning application 2342539

Permission for the construction of a new substation building within a car park permitted under Council Ref…

Hollyhill Industrial Estate, Kilmore Heights, Hollyhill

Decision

Granted with conditions

Construction status

Construction commenced

Latest milestone

Completion certificate validated (1 unit)

18 Dec 2024

Application timeline

Key milestones

Planning, appeal and official building-control milestones.

  1. Application received

  2. Decision: CONDITIONAL

  3. Final grant

  4. Works commenced

    Official NBCO/BCMS data
  5. Completion certificate validated (1 unit)

    Official NBCO/BCMS data

Application details

Planning reference
2342539
Council
Cork City Council
Proposal description
Permission for the construction of a new substation building within a car park permitted under Council Ref: 22/41121 to cater for additional electrical vehicle (EV) charging points at Hollyhill Industrial Estate, Hollyhill, Cork, T23YK84. The proposed substation building will include a medium voltage switch room, electrical distribution room and all associated site development works
Location / address
Hollyhill Industrial Estate, Kilmore Heights, Hollyhill
Application type
PERMISSION
Received / registered
14 Dec 2023
Council decision
CONDITIONAL
Council decision date
15 Feb 2024
Final grant date
25 Mar 2024