Within the townlands of Gilbertstown and Bendinstown, Co. Carlow, Ireland
Carlow County Council2560155Registered 9 Jun 2025
Under appeal
A 10 year permission for a Battery Energy Storage system.
Latest activity
Appeal lodged · 24 Mar 2026
Planning by development type
Significant utility, grid, telecommunications and other infrastructure developments.
1 currently active in Carlow · 800 identified in total
Filter by local authority.
Latest activity
Carlow County Council2560155Registered 9 Jun 2025
Under appeal
A 10 year permission for a Battery Energy Storage system.
Latest activity
Appeal lodged · 24 Mar 2026
Carlow County Council2460410Registered 16 Dec 2024
CONDITIONAL
• The replacement (“restringing”) of the existing overhead line circuit conductor wires…
Latest activity
Final grant · 9 Jul 2025
Carlow County Council2460319Registered 7 Oct 2024
Invalid or incomplete
For development consisting of works along the ca.
Carlow County Council2460223Registered 30 Jul 2024
CONDITIONAL
Of 110kV underground electricity cabling and all associated ancillary site development works.
Latest activity
Final grant · 23 Oct 2024
Carlow County Council2460045Registered 29 Feb 2024
Invalid or incomplete
For thirty-year permission for a grid system services facility located at Gortawee, Mucklagh, Ballyconnell, County Cavan…
Carlow County Council22199Registered 15 Jun 2022
CONDITIONAL
To apply for a 10 year permission for the proposed development of an underground electricity interconnector cable.
Latest activity
Final grant · 9 Sept 2022
Carlow County Council22163Registered 20 May 2022
CONDITIONAL
For a 10 year planning permission for a solar farm and associated works…
Latest activity
Final grant · 22 Mar 2023
Carlow County Council22142Registered 28 Apr 2022
Invalid or incomplete
For a solar farm which will connect to the national grid on lands with a total area of circa 128 hectares…
Carlow County Council21445Registered 17 Nov 2021
Grant permission with revised conditions
Permission for a 10 year planning permission for the development of a synchronous condenser grid support facility…
Latest activity
Appeal decision · 2 May 2024
Carlow County Council21389Registered 13 Oct 2021
Invalid or incomplete
Permission for a 10 year planning permission for the development of a synchronous condenser grid support facility…
Carlow County Council19322Registered 16 Aug 2019
CONDITIONAL
Permission for the erection of a 22.5m monopole to support telecommunications antennae for use by Eir…
Latest activity
Appeal decision · 31 Aug 2020
Carlow County Council19276Registered 12 Jul 2019
Invalid or incomplete
The erection of a 21m monopole to support telecommunications antennae for use by Eir and other operators…
Carlow County Council1823Registered 1 Feb 2018
CONDITIONAL
Ten year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide…
Latest activity
Appeal decision · 23 Sept 2019
Carlow County Council1813Registered 18 Jan 2018
Invalid or incomplete
Ten year planning permission for the development of an up to 100MW Battery Energy Storage Facility that will provide…
Carlow County Council17309Registered 25 Oct 2017
CONDITIONAL
The construction of 21m high telecommunications monopole support structure…
Latest activity
Appeal decision · 7 Aug 2018
Carlow County Council1748Registered 23 Feb 2017
REFUSED
Permission for the construction of telecommunications infrastructure comprising of…
Latest activity
Appeal decision · 28 Feb 2019
Carlow County Council177Registered 12 Jan 2017
Withdrawn
Planning Permission to construct a 21m high telecommunications monopole support structure carrying antennas…
Carlow County Council1436Registered 18 Feb 2014
Status not classified