OpenList

Planning application 2113

Seven-Turbine Wind Farm, Rossacurra, Co. Carlow

Rossacurra Cranemore Kilbrannish North Bealalaw Raheenliegh Aclare Co. Carlow

Current status

Under appeal

Council status: APPLICATION FINALISED

Latest milestone

Appeal lodged with An Coimisiún Pleanála

15 Dec 2023

Application timeline

Key milestones

Council and An Coimisiún Pleanála milestones.

  1. Application received

  2. Decision: REFUSED

  3. Appeal lodged with An Coimisiún Pleanála

    Official An Coimisiún Pleanála dataView appeal case
  4. Appeal decision: Refuse Permission

    Official An Coimisiún Pleanála dataView appeal case
  5. Appeal lodged with An Coimisiún Pleanála

    Official An Coimisiún Pleanála dataView appeal case

Application details

Planning reference
2113
Council
Carlow County Council
Proposal description
Permission to develop a wind farm and associated works . The proposed development will consist of: - Construction of up to 7 no. wind turbines with a maximum overall blade tip height of up to 178m; - Construction of turbine foundations and crane pad hardstanding areas; - Construction of new site tracks and associated drainage infrastructure; - Upgrading of existing tracts and associated drainage infrastructure where necessary including upgrade of entrance onto L2026; - All associated drainage and sediment control including the installation of new watercourse or drain crossings and the re-use or upgrading of existing internal watercourse and drain crossings; - Construction of 1 no. permanent onsite 38kV electrical substation to ESBN specifications including: Control building with welfare facilities; - Electrical infrastructure; - Parking; - Wastewater holding tank; - rainwater harvesting; - Security fencing; - All associated infrastructure, services and site works; - 1 no. temporary construction site compound and associated ancillary infrastructure including parking; - 1 no. on site borrow pit (the borrow pit shall be accessed via wind farm access tracks); - Tree felling to facilitate construction and operation of the proposed development; - Installation of medium voltage (20/33kV) and communication underground cabling between the proposed turbines and the proposed on-site substation and associated ancillary works; - Erection of 1 no. permanent meteorological mast to a maximum height of 100m above ground level; - Upgrade of existing forest tracks and paths that shall be re-purposed as recreational amenity trails for community use including signage; - All associated site development works; - A 10 year planning permission and 35 year operational life from the date of commissioning of the entire wind farm. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared in respect of the proposed development and will be submitted with the application.
Location / address
Rossacurra Cranemore Kilbrannish North Bealalaw Raheenliegh Aclare Co. Carlow
Application type
PERMISSION
Received / registered
22 Jan 2021
Valid date
22 Jan 2021
Council status
APPLICATION FINALISED
Council decision
Refused
Council decision date
18 Mar 2021
Appeal lodged
15 Dec 2023

Location context

Nearby sold prices

OpenList shows sold-price context only where a reliable proximity, Eircode or locality relationship can be established.

Explore sold prices
No reliable nearby sold-price match is available for this record. OpenList does not infer an exact property match from an address alone.