2560469
25 Nov 2025
Status: DECISION MADE
permission to erect a 850 kW wind turbine located in the northern area of our existing plant, with a hub height of 65 metres and a blade radius of 26 metres, together with underground ducting connecting to the existing ESB substation and all associated site works. A Natura Impact Assessment (NIS) will be submitted to the Planning Authority in connection with the application described above. This development is covered by the provisions of the Renewable Energy Directive III (Directive (EU) 2023/2413). Significant further information received relates to submitted revised CEMP, Ornithology report, Revised Natura Impact report, Water framework compliance assessment and Updated planning report.
Monaghan County Council
Dundrumman , Scotstown , Co. Monaghan