Planning application 4144/24

Permission for development will consist of refurbishment, renovation…

Port Centre, Alexandra Road, Dublin Port, Dublin 1 D01H4C6

Decision

GRANT PERMISSION

Construction status

Construction commenced

Official building-control evidence dated 27 Feb 2026.

Matched phased building-control records

Source: NBCO/BCMS open data

An official council link is not available for this recorded application.

Application details

Planning reference
4144/24
Council
Dublin City Council
Proposal description
Permission for development will consist of refurbishment, renovation and retrofitting works to an existing building (Dublin Port Centre and associated ancillary works, comprising: Reglazing and insulation upgrades to all building facades to include installation of louvres (brise soleil type); Revisions at roof level to include replacement of existing roof slab, construction of enclosed viewing gallery (c. 36sq.m) and open-air external accessible deck, reconfiguration of existing plant areas and antennae and provision for plant relocated from fifth floor level, all resulting in a revised total building height (excluding antennae) of c. 36.25m (increased from 34.15m) and a reduction of 39sq.m in gross floor area (GFA) to 60sq.m total; Removal of existing signs (2 no. signs of 9.2sq m each) on the northern and southern façades and provision for 3 no. illuminated corporate signs (combined C. 42.5sq.m) at roof level on the northern, southern and western facades; Internal layout modifications to provide for improved floorplates to include Lower Ground Floor GFA to be reduced by c. 11sq.m to c. 1407sq.m, Ground Floor GFA to be reduced by c. 45sq.m to c. 509sq.m and to include an extended mezzanine over ground floor level of C. 233sq.m (an increase of C. 82sq.m); Increase of GFA at fifth floor level from C. 440sq.m to C. 685sq.m (an increase of C. 245sq.m), facilitated by existing plant removal and relocation. Other associated works to include existing car park layout modifications resulting in a reduction of parking spaces (from 90 no. permitted spaces to 83 no. spaces), installation of electric vehicle charging units at 19 no. existing vehicle parking spaces (of which 2 no. are accessible spaces), provision of photovoltaic (PV) canopies (c. 700sq.m, 4.46m high) over car parking spaces; construction of a new ESB substation (c. 37sq.m, 3m high) and bicycle storage shed (c. 28.5sq.m, 3m high) and all other site works to include site clearance, landscaping, revised utilities and drainage arrangements.
Location / address
Port Centre, Alexandra Road, Dublin Port, Dublin 1 D01H4C6
Application type
Permission
Received / registered
12 Aug 2024
Council decision
GRANT PERMISSION
Council decision date
2 Oct 2024
Final grant date
20 Nov 2024

Planning and construction timeline

Key dated milestones from planning, appeal and official building-control records.

  1. Application received

  2. Decision: GRANT PERMISSION

  3. Final grant

  4. Works commenced

    Official NBCO/BCMS data
  5. Works commenced

    Official NBCO/BCMS data

Location context

Nearby sold prices

Recent Property Price Register sales in Dublin 1. Distances are not shown because the sale records do not contain reliable coordinates.

Explore sold prices